Development Process:
PRE-APPLICATION PROCESS
Town Planner and Staff
Application Determination
Special Permit Application
Subdivision/Re-subdivision Application
ZBA
Inland Wetlands
State & Other
APPLICATION SUBMITTAL
Application Distribution
For Staff Review
ZBA (if necessary)
Inland
Wetlands
Special Permit/Subdivision
Other
STAFF REVIEW
Town Engineer Review
Fire Marshal Review
Town Sanitarian Review
Town Planner Report
LOCAL AGENCY APPROVAL
(If
Necessary)
Wetlands Approval
WPCA Approval
Zoning Board
Of Appeals Approval
STATE AGENCY APPROVAL
(If
Necessary)
Conndot Review
DEP
DHS
DPUC
Regional
Planning Agency
PLANNING & ZONING RECEIPT
Hearing Date Set
or
Administrative Approval
Max Time: 65
Days
PUBLIC HEARING
Wetland Approval
In Place
Max Time: 30 Days
APPLICATION DECISION
Approval/Denial
Max Time: 65 Days
FILING WITH TOWN CLERK
Bond In Place
BUILDING PERMIT APPLICATION
Max Time: 30
Days
CERTIFICATE OF OCCUPANCY
As-Built
Survey Submitted
Certificate of Occupancy Issued
Max Time: 10
Days
COMPLETED PROJECT
Bond
Release
Contact us for more info