Development Process:


PRE-APPLICATION PROCESS
Town Planner and Staff
Application Determination
• Special Permit Application •
• Subdivision/Re-subdivision Application •
• ZBA •
• Inland Wetlands •
• State & Other •

APPLICATION SUBMITTAL
Application Distribution For Staff Review
• ZBA (if necessary) •
• Inland Wetlands •
• Special Permit/Subdivision •
• Other •

STAFF REVIEW
Town Engineer Review
Fire Marshal Review
Town Sanitarian Review
Town Planner Report

LOCAL AGENCY APPROVAL
(If Necessary)
Wetlands Approval
WPCA Approval
Zoning Board Of Appeals Approval

STATE AGENCY APPROVAL
(If Necessary)
Conndot Review
DEP
DHS
DPUC
Regional Planning Agency

PLANNING & ZONING RECEIPT
Hearing Date Set
or
Administrative Approval
• Max Time: 65 Days •

PUBLIC HEARING
Wetland Approval In Place
• Max Time: 30 Days •

APPLICATION DECISION
Approval/Denial
• Max Time: 65 Days •

FILING WITH TOWN CLERK
Bond In Place

BUILDING PERMIT APPLICATION
• Max Time: 30 Days •

CERTIFICATE OF OCCUPANCY
As-Built Survey Submitted
Certificate of Occupancy Issued
• Max Time: 10 Days •

COMPLETED PROJECT
Bond Release





Contact us for more info


image




Contact us | View site map | Employee Email
News & Information
Results of the Main Street Charrette!:
Please see the Local News section of the Website to see the final presentation and results of the Main Street Charrette that was sponsored by UCONN.
Hebron Farmer's Market 2013
  Every Saturday
  Jun 15 - Oct 12
  For more information, Click Here.
Bifurcation in ConnecticutClick Here.
Core Services InformationClick Here.
Town Hall Streams, Click Here. 

HEBRON ALERTS NOTIFICATION SYSTEM

 

Direct Energy

Direct Choice Program
Promotion Code: hebronct



©Copyright 2009 Town of Hebron All Rights Reserved
For more information feel free to Contact Us